As a project manager
Respuesta :
creeds25
creeds25
07-02-2018
Total number of hours=18 hrs
Number of engineers=3
So divide number of hours by number of engineers.
18/3=6 hours
Answer: Option A 6
Answer Link
VER TODAS LAS RESPUESTAS ( 41+ )
Otras preguntas
If an object is dropped from the height of 54 feet, the function h = -16t² + 54 gives the height of the object after t seconds. Approximately how long will i
describe the affect of the globalzation on air pollution in china l
Poverty is the major cause of human trafficking. Justify in 50-100 words.
One corner of a square is folded to its centre to form an irregular pentagon. The areas of the pentagon and of the square are consecutive integers. What is the
Find the final value and the compound interest if $8000 is invested for 2 years at 27% p.a.
Harlem dream deferred what dream do you think he might be referring to?
Whats the 20,21,22,23,24,25,26 and 27th amendments in your own words doesn't have to be long
What are all the factors of the number 90? A) 3, 5, 6, 9, 10, 15, 18, and 30 B) 1 and 90 C) 1, 2, 3, 5, 6, 9, 10, 15, 18, 30, 45, and 90 D) 1, 2, 3, 30, 45, and
Find the 100th term of an=17-4(n-1)
How much do you have to add to 3/2 to make it equal to the sum of 11/5 and 4 1/2?