Cerezo Corporation uses the following activity rates from its activity-based costing to assign overhead costs to products:

Activity Cost Pools Activity Rate
Assembling products $2.86 per assembly hour
Processing customer orders $48 .23 per customer order
Setting up batches $76.23 per batch

Data for one of the company's products follow:

Product Q79P
Number of assembly hours 252
Number Of customer orders 42
Number OE batches 68

How much overhead cost would be assigned to Product Q79P using the activity-based costing system?