Pennsylvania Company supplied the following information:

Direct materials$70 per unit
Direct labor$5 per unit
Factory overhead$62 per machine hour
Number of units in Job 99100
Direct labor hours worked on Job 9920
Direct labor dollars spent on Job 99$500
Machine hours used on Job 99 10

Total job cost for Job 99 is:

a.$1,820

b.$8,120

c.$8,740

d.$12,620

e.None of the above

Respuesta :

Answer:

$12,620

Explanation:

Cost of Direct materials of Job 99 = $70 x 100 = $7,000

Cost of Direct labour of Job 99 = $5 x 100 = $5,000

Overhead Expenses of Job 99 = $62 x 10 = $620

Total job cost for Job 99 = 7000 + 5000 +620 = $12,620

Answer:

D

Explanation: