Respuesta :

Answer:

$5,000

Explanation:

Given that,

Direct material cost = $2,000

Direct labor cost = $3,000

Prime cost is the sum total of direct material and direct labor cost.

Prime cost:

= Direct material cost + Direct labor cost

= $2,000 + $3,000

= $5,000

Therefore, the prime cost is $5,000.