Activities A, B, and C are part of the same project. Activity A is worth $200, is 100% complete, and actually cost $200. Activity B is worth $75, is 90% complete, and actual cost $120 so far. Activity C is worth $200, is 75% complete, and has cost $175 so far. The total budget is $1,000. What is the Cost Variance (CV) for the project